HORIZON
CASRI
Collaborative Action coordinating and enhancing systemic, actionable and transversal Sustainability Research and Innovation
- Programme
- Horizon Europe
- Started
- Ends
- Duration
- 32 months
- Total cost
- EUR 1,999,860
- EU contribution
- EUR 1,999,860
- Participants
- 18 from 14 countries
- Topic
- HORIZON_HORIZON-WIDERA-2023-ERA-01-01
- Grant agreement
- 101131520
Coordinated by Umweltbundesamt (DEGermany).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Umweltbundesamt | DEGermany | Coordinator | EUR 434,301 | known name (0.97) |
| Umweltbundesamt Gesellschaft Mit Beschrankter Haftung (Uba GmbH) | ATAustria | Participant | EUR 118,158 | PIC (1.00) |
| Vlaamse Gewest | BEBelgium | Participant | EUR 111,595 | PIC (1.00) |
| Bulgarian Academy of Sciences | BGBulgaria | Participant | EUR 55,938 | PIC (1.00) |
| Akademie der Naturwissenschaften Schweiz Scnat | CHSwitzerland | Participant | EUR 46,563 | PIC (1.00) |
| Federal Department for Environment, Transport, Energy and Communications | CHSwitzerland | Participant | EUR 55,625 | PIC (1.00) |
| European Environment Agency | DKDenmark | Associated partner | EUR 0 | known name (0.95) |
| Suomen Ymparistokeskus | FIFinland | Participant | EUR 208,750 | known name (0.95) |
| Bureau de Recherches Geologiques et Minieres | FRFrance | Participant | EUR 175,958 | known name (0.95) |
| Ministere de la Transition Ecologique, de L'Energie, du Climat et de la Prevention des Risques | FRFrance | Participant | EUR 82,500 | known name (0.95) |
| Natural Resources Body for Wales | GBUnited Kingdom | Participant | EUR 86,250 | PIC (1.00) |
| Environmental Protection Agency | IEIreland | Participant | EUR 26,250 | known name (0.95) |
| Istituto Superiore Per la Protezione e la Ricerca Ambientale | ITItaly | Participant | EUR 63,750 | PIC (1.00) |
| T6 Ecosystems SRL | ITItaly | Participant | EUR 207,750 | PIC (1.00) |
| Ministarstvo Ekonomije | MEMontenegro | Participant | EUR 44,688 | PIC (1.00) |
| Ministerie van Infrastructuur en Waterstaat | NLNetherlands | Participant | EUR 116,250 | known name (0.95) |
| Stichting Deltares | NLNetherlands | Participant | EUR 117,099 | known name (0.95) |
| Slovenska Agentura Zivotneho Prostredia | SKSlovakia | Participant | EUR 48,438 | known name (0.95) |
Changes of the consortium
First seen on with 18 participants from 14 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.