Skip to content

H2020

EENVEST

Risk reduction for Building Energy Efficiency investments

Programme
Horizon 2020
Started
Ends
Duration
36 months
Total cost
EUR 1,494,538
EU contribution
EUR 1,494,538
Participants
11 from 5 countries
Topic
H2020_LC-SC3-EE-10-2018-2019-2020
Grant agreement
833112

Coordinated by Accademia Europea di Bolzano (ITItaly).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Accademia Europea di BolzanoITItalyCoordinatorEUR 276,875PIC (1.00)
EnerginvestBEBelgiumParticipantEUR 192,125PIC (1.00)
Mac ManagementBEBelgiumThird partyNot statedPIC (1.00)
Union Internationale de la Propriete ImmobiliereBEBelgiumParticipantEUR 80,703PIC (1.00)
Ecrowd Invest Plataforma de Financiacion Participativa SLESSpainParticipantEUR 55,543PIC (1.00)
Global New Energy Finance SLESSpainParticipantEUR 179,810PIC (1.00)
R2M Solution Spain SLESSpainThird partyNot statedPIC (1.00)
R2M SolutionFRFranceParticipantEUR 183,500PIC (1.00)
Integrated Environmental Solutions LimitedGBUnited KingdomParticipantEUR 244,250PIC (1.00)
Politecnico di MilanoITItalyParticipantEUR 97,500known name (0.95)
Sinloc-Sistema Iniziative Locali SpAITItalyParticipantEUR 184,233PIC (1.00)

Changes of the consortium

First seen on with 11 participants from 5 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.