Skip to content

FP7

LNG BLUE CORRIDORS

LNG-BC: Liquefied Natural Gas Blue Corridors

Programme
Seventh Framework Programme
Started
Ends
Duration
48 months
Total cost
EUR 14,336,091
EU contribution
EUR 7,962,696
Participants
27 from 11 countries
Topic
FP7_GC.SST.2012.2-3.
Grant agreement
321592

Coordinated by Idiada Automotive Technology SA (ESSpain).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Idiada Automotive Technology SAESSpainCoordinatorEUR 2,221,962PIC (1.00)
Drive Systems NVBEBelgiumParticipantEUR 424,734PIC (1.00)
Fluxys Belgium SABEBelgiumParticipantEUR 31,906known name (0.95)
Vlaamse Instelling Voor Technologisch Onderzoek N.V.BEBelgiumParticipantEUR 468,218PIC (1.00)
Erdgas Mobil GmbHDEGermanyParticipantEUR 384,782PIC (1.00)
Linde AGDEGermanyParticipantEUR 7,854PIC (1.00)
Asociacion Ngva EuropeESSpainParticipantEUR 370,500PIC (1.00)
Ham Criogenica SLESSpainParticipantEUR 104,852PIC (1.00)
Iveco Espana SLESSpainParticipantEUR 115,931PIC (1.00)
Mendyra SLESSpainParticipantEUR 4,800PIC (1.00)
Monfort Logistica S.L.ESSpainParticipantEUR 100,800PIC (1.00)
Naturgy Energy Group SAESSpainParticipantEUR 212,400known name (0.95)
Gnvert SasFRFranceParticipantEUR 471,861PIC (1.00)
Renault Trucks SasFRFranceParticipantEUR 260,008PIC (1.00)
Westport Power FranceFRFranceParticipantEUR 60,293PIC (1.00)
Gasrec LtdGBUnited KingdomParticipantEUR 31,650PIC (1.00)
T. Baden Hardstaff LimitedGBUnited KingdomParticipantEUR 454,990PIC (1.00)
Energetski Institut Hrvoje PozarHRCroatiaParticipantEUR 51,650known name (0.95)
Centro Ricerche Fiat ScpaITItalyParticipantEUR 258,876PIC (1.00)
Eni SpAITItalyParticipantEUR 394,440known name (0.95)
Ballast Nedam International Product Management B.V.NLNetherlandsParticipantEUR 8,400PIC (1.00)
Cloud Energy LdaPTPortugalParticipantEUR 185,025PIC (1.00)
Galp Power SAPTPortugalParticipantEUR 207,300PIC (1.00)
Gold Energy -Comercializadora de Energia SA-GoldenergyPTPortugalParticipantEUR 163,200PIC (1.00)
Energigas Sverige Service ABSESwedenParticipantEUR 275,591PIC (1.00)
Volvo Technology ABSESwedenParticipantEUR 423,450PIC (1.00)
Enos Lng, Druzba za Raziskave, Razvoj, Uvajanje in Uporabo Technologij na Podrocju Energetike DooSISloveniaParticipantEUR 267,225PIC (1.00)

Changes of the consortium

First seen on with 27 participants from 11 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.