Skip to content

FP7

SICMA

Simulation of Crisis Management Activities

Programme
Seventh Framework Programme
Started
Ends
Duration
30 months
Total cost
EUR 3,902,633
EU contribution
EUR 2,566,330
Participants
9 from 6 countries
Topic
FP7_SEC-2007-6.1-02
Grant agreement
217855

Coordinated by Selex Sistemi Integrati SpA (ITItaly).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Selex Sistemi Integrati SpAITItalyCoordinatorEUR 526,830PIC (1.00)
Cess GmbH Centre for European Security StrategiesDEGermanyParticipantEUR 237,000PIC (1.00)
Industrieanlagen Betriebsgesellschaft MbhDEGermanyParticipantEUR 120,250PIC (1.00)
Ifad Ts A/SDKDenmarkParticipantEUR 399,200PIC (1.00)
Skytek LimitedIEIrelandParticipantEUR 222,250PIC (1.00)
Elbit Systems LtdILIsraelParticipantEUR 403,570PIC (1.00)
Elsag Datamat S.P.A.ITItalyParticipantNot statedPIC (1.00)
Universita Cattolica del Sacro CuoreITItalyParticipantEUR 152,710known name (0.95)
Itti Sp ZooPLPolandParticipantEUR 213,800PIC (1.00)

Changes of the consortium

First seen on with 9 participants from 6 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.