H2020
RESIN
Climate Resilient Cities and Infrastructures
- Programme
- Horizon 2020
- Started
- Ends
- Duration
- 42 months
- Total cost
- EUR 7,466,005
- EU contribution
- EUR 7,466,005
- Participants
- 17 from 8 countries
- Topic
- H2020_DRS-09-2014
- Grant agreement
- 653522
Coordinated by Nederlandse Organisatie Voor Toegepast Natuurwetenschappelijk Onderzoek Tno (NLNetherlands).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Nederlandse Organisatie Voor Toegepast Natuurwetenschappelijk Onderzoek Tno | NLNetherlands | Coordinator | EUR 933,688 | known name (0.95) |
| Siemens Aktiengesellschaft Oesterreich | ATAustria | Participant | EUR 47,853 | PIC (1.00) |
| Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung Ev | DEGermany | Participant | EUR 921,875 | known name (0.95) |
| Iclei European Secretariat GmbH (Iclei Europasekretariat GmbH) | DEGermany | Participant | EUR 869,625 | PIC (1.00) |
| Siemens Aktiengesellschaft | DEGermany | Participant | EUR 536,035 | PIC (1.00) |
| Asociacion BC3 Basque Centre for Climate Change - Klima Aldaketa Ikergai | ESSpain | Participant | EUR 258,876 | VAT number (0.97) |
| Ayuntamiento de Bilbao | ESSpain | Participant | EUR 219,860 | known name (0.95) |
| Fundacion Tecnalia Research & Innovation | ESSpain | Participant | EUR 641,625 | PIC (1.00) |
| Ecole des Ingenieurs de la Ville Deparis | FRFrance | Participant | EUR 630,875 | PIC (1.00) |
| Oldham Metropolitan Borough Council | GBUnited Kingdom | Participant | EUR 233,088 | known name (0.95) |
| The University of Manchester | GBUnited Kingdom | Participant | EUR 865,735 | known name (0.95) |
| Arcadis Nederland BV | NLNetherlands | Participant | EUR 159,788 | PIC (1.00) |
| Stichting Koninklijk Nederlands Normalisatie Instituut | NLNetherlands | Participant | EUR 235,335 | PIC (1.00) |
| Uniresearch BV | NLNetherlands | Participant | EUR 160,166 | PIC (1.00) |
| Itti Sp Zoo | PLPoland | Participant | EUR 390,125 | PIC (1.00) |
| Hlavne Mesto Slovenskej Republiky Bratislava | SKSlovakia | Participant | EUR 210,989 | known name (0.95) |
| Univerzita Komenskeho v Bratislave | SKSlovakia | Participant | EUR 150,469 | known name (0.95) |
Changes of the consortium
First seen on with 17 participants from 8 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.