Skip to content

FP7

SARABAND

Smart Antenna & Radio for Access and Backhaul for Advanced Network noDes

Programme
Seventh Framework Programme
Started
Ends
Duration
42 months
Total cost
EUR 5,027,496
EU contribution
EUR 3,001,277
Participants
9 from 5 countries
Topic
FP7_ICT-2011.3.2
Grant agreement
288267

Coordinated by Thales Six Gts France Sas (FRFrance).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Thales Six Gts France SasFRFranceCoordinatorEUR 690,977PIC (1.00)
Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung EvDEGermanyParticipantEUR 345,155known name (0.95)
Fibernova Systems SLESSpainParticipantEUR 222,436PIC (1.00)
Universitat Politecnica de ValenciaESSpainParticipantEUR 183,790known name (0.95)
Hcm.systrelFRFranceParticipantEUR 150,720PIC (1.00)
Systrel SasFRFranceParticipantEUR 74,316PIC (1.00)
ThalesFRFranceParticipantEUR 441,574PIC (1.00)
Bluwan UK LimitedGBUnited KingdomParticipantEUR 348,097PIC (1.00)
Orteh SpzooPLPolandParticipantEUR 227,000PIC (1.00)

Changes of the consortium

First seen on with 9 participants from 5 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.