H2020
BIPVBOOST
Bringing down costs of BIPV multifunctional solutions and processes along the value chain, enabling widespread nZEBs implementation
- Programme
- Horizon 2020
- Started
- Ends
- Duration
- 56 months
- Total cost
- EUR 11,434,539
- EU contribution
- EUR 8,844,070
- Participants
- 21 from 7 countries
- Topic
- H2020_LC-SC3-RES-6-2018
- Grant agreement
- 817991
Coordinated by Fundacion Tecnalia Research & Innovation (ESSpain).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Fundacion Tecnalia Research & Innovation | ESSpain | Coordinator | EUR 903,125 | PIC (1.00) |
| 3E | BEBelgium | Participant | EUR 425,491 | PIC (1.00) |
| Icares Consulting | BEBelgium | Participant | EUR 263,592 | PIC (1.00) |
| Optimal Computing | BEBelgium | Participant | EUR 206,391 | PIC (1.00) |
| Ernst Schweizer AG | CHSwitzerland | Participant | EUR 400,531 | PIC (1.00) |
| Flisom AG | CHSwitzerland | Participant | EUR 598,416 | PIC (1.00) |
| Scuola Universitaria Professionale della Svizzera Italiana | CHSwitzerland | Participant | EUR 1,296,083 | PIC (1.00) |
| Viriden + Partner AG | CHSwitzerland | Participant | EUR 243,775 | PIC (1.00) |
| Wirtschaft und Infrastruktur GmbH & Co Planungs KG | DEGermany | Participant | EUR 279,650 | PIC (1.00) |
| Comsa Corporacion de Infraestructuras SL | ESSpain | Third party | Not stated | PIC (1.00) |
| Comsa Instalaciones y Sistemas Industriales SA | ESSpain | Third party | Not stated | PIC (1.00) |
| Comsa Sau | ESSpain | Participant | EUR 238,437 | PIC (1.00) |
| Instituto de Sistemas Fotovoltaicosde Concentracion SA | ESSpain | Participant | EUR 141,465 | PIC (1.00) |
| Mondragon Assembly Sociedad Cooperativa | ESSpain | Participant | EUR 824,994 | PIC (1.00) |
| Onyx Solar Energy SL | ESSpain | Participant | EUR 832,125 | PIC (1.00) |
| Centre Scientifique et Technique du Batiment | FRFrance | Participant | EUR 241,375 | PIC (1.00) |
| Cycleco Sas | FRFrance | Participant | EUR 348,688 | PIC (1.00) |
| Enerbim | FRFrance | Participant | EUR 323,663 | PIC (1.00) |
| Accademia Europea di Bolzano | ITItaly | Participant | EUR 359,063 | PIC (1.00) |
| Piz SRL | ITItaly | Participant | EUR 443,397 | PIC (1.00) |
| Tulipps BV | NLNetherlands | Participant | EUR 473,813 | PIC (1.00) |
Changes of the consortium
First seen on with 21 participants from 7 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.