H2020
EnFAIT
Enabling Future Arrays in Tidal
- Programme
- Horizon 2020
- Started
- Ends
- Duration
- 72 months
- Total cost
- EUR 20,204,450
- EU contribution
- EUR 14,914,600
- Participants
- 13 from 5 countries
- Topic
- H2020_LCE-15-2016
- Grant agreement
- 745862
Coordinated by Nova Innovation Ltd (GBUnited Kingdom).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Nova Innovation Ltd | GBUnited Kingdom | Coordinator | EUR 9,991,164 | PIC (1.00) |
| Agence Intercommunale de Developpement des Arrondissements de Tournai D'Ath et de Communes Avoisinantes | BEBelgium | Participant | EUR 397,828 | PIC (1.00) |
| Skf GmbH | DEGermany | Participant | EUR 1,220,993 | PIC (1.00) |
| Skf Marine GmbH | DEGermany | Third party | Not stated | PIC (1.00) |
| Rsk Environnement | FRFrance | Participant | EUR 283,290 | PIC (1.00) |
| Wood Group France Sas | FRFrance | Participant | EUR 341,355 | PIC (1.00) |
| Hmk Technical Services Limited | GBUnited Kingdom | Participant | EUR 0 | PIC (1.00) |
| James Fisher Marine Services Limited | GBUnited Kingdom | Participant | EUR 35,459 | PIC (1.00) |
| Mojo Maritime Limited | GBUnited Kingdom | Participant | EUR 72,897 | PIC (1.00) |
| Offshore Renewable Energy Catapult | GBUnited Kingdom | Participant | EUR 1,497,825 | known name (0.95) |
| Skf (U.K) Limited | GBUnited Kingdom | Third party | Not stated | PIC (1.00) |
| The University of Edinburgh | GBUnited Kingdom | Participant | EUR 1,073,790 | known name (0.95) |
| Skf BV | NLNetherlands | Third party | Not stated | PIC (1.00) |
Changes of the consortium
First seen on with 13 participants from 5 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.