Skip to content

FP7

GE2O

Geo-clustering to deploy the potential of Energy efficient Buildings across EU

Programme
Seventh Framework Programme
Started
Ends
Duration
24 months
Total cost
EUR 1,494,304
EU contribution
EUR 995,000
Participants
12 from 10 countries
Topic
FP7_EeB.NMP.2011-4
Grant agreement
285501

Coordinated by Centre Scientifique et Technique du Batiment (FRFrance).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Centre Scientifique et Technique du BatimentFRFranceCoordinatorEUR 147,914PIC (1.00)
BuildwiseBEBelgiumParticipantEUR 69,456PIC (1.00)
European Construction and Sustainable Built Environment Technology PlatformBEBelgiumParticipantEUR 82,362PIC (1.00)
Technicky a Zkusebni Ustav Stavebni Praha S. P.CZCzechiaParticipantEUR 79,180PIC (1.00)
Acciona Construccion SAESSpainParticipantEUR 88,275PIC (1.00)
Institute for SustainabilityGBUnited KingdomParticipantEUR 59,064PIC (1.00)
Politecnico di MilanoITItalyParticipantEUR 60,188known name (0.95)
Rina Consulting SpAITItalyParticipantEUR 151,405PIC (1.00)
Arcelormittal Belval & Differdange SALULuxembourgParticipantEUR 84,744PIC (1.00)
Nederlandse Organisatie Voor Toegepast Natuurwetenschappelijk Onderzoek TnoNLNetherlandsParticipantEUR 60,394known name (0.95)
Asm Research Solutions Strategy Spolka z Ograniczona OdpowiedzialnosciaPLPolandParticipantEUR 52,430PIC (1.00)
Zavod za Gradbenistvo SlovenijeSISloveniaParticipantEUR 59,588known name (0.95)

Changes of the consortium

First seen on with 12 participants from 10 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.