FP7
ERRAC ROAD MAP
ERRAC Road Map
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 38 months
- Total cost
- EUR 1,683,513
- EU contribution
- EUR 1,540,994
- Participants
- 18 from 8 countries
- Topic
- FP7_SST.2008.2.5.1
- Grant agreement
- 234255
Coordinated by Union Internationale des Chemins de Fer (FRFrance).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Union Internationale des Chemins de Fer | FRFrance | Coordinator | EUR 396,605 | PIC (1.00) |
| Community of European Railway and Infrastructure Companies | BEBelgium | Participant | EUR 74,546 | PIC (1.00) |
| European Passengers' Federation Ivzw | BEBelgium | Participant | EUR 46,115 | PIC (1.00) |
| European Rail Infrastructure Managers Asbl | BEBelgium | Participant | EUR 12,970 | PIC (1.00) |
| Union des Industries Ferroviaires Europeennes - Unife | BEBelgium | Participant | EUR 226,840 | PIC (1.00) |
| Union Internationale des Transports Publics | BEBelgium | Participant | EUR 187,887 | PIC (1.00) |
| Eurnex e. v. | DEGermany | Participant | EUR 49,969 | PIC (1.00) |
| Knorr-Bremse Systeme Fur Schienenfahrzeuge GmbH | DEGermany | Participant | EUR 38,787 | PIC (1.00) |
| Societe Nationale Sncf | FRFrance | Participant | EUR 40,125 | known name (0.95) |
| Network Rail Infrastructure Limited | GBUnited Kingdom | Participant | EUR 41,080 | known name (0.95) |
| Hitachi Rail Sts SpA | ITItaly | Participant | EUR 40,125 | PIC (1.00) |
| Italcertifer Societa Per Azioni | ITItaly | Participant | EUR 27,552 | PIC (1.00) |
| Mer Mec SpA | ITItaly | Participant | EUR 32,501 | PIC (1.00) |
| Rete Ferroviaria Italiana | ITItaly | Participant | EUR 16,585 | known name (0.95) |
| Trenitalia SpA | ITItaly | Participant | EUR 44,137 | known name (0.95) |
| European Federation of Railways Trackworks Contractors | LULuxembourg | Participant | EUR 26,884 | PIC (1.00) |
| Instituto Superior Tecnico | PTPortugal | Participant | EUR 28,203 | known name (0.95) |
| Alstom Rail Sweden AB | SESweden | Participant | EUR 50,825 | PIC (1.00) |
Changes of the consortium
First seen on with 18 participants from 8 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.