Knowledge-based energy management for public buildings through holistic information modeling and 3D visualization

Programme
Seventh Framework Programme
Started
Ends
Duration
36 months
Total cost
EUR 4,468,165
EU contribution
EUR 3,198,131
Participants
13 from 6 countries
Topic
FP7_EEB-ICT-2011.6.4
Grant agreement
285229

Coordinated by Building Research Establishment Ltd (GBUnited Kingdom).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Building Research Establishment LtdGBUnited KingdomCoordinatorEUR 476,500PIC (1.00)
Karlsruher Institut fuer TechnologieDEGermanyParticipantEUR 626,968known name (0.95)
Steinbeis Innovation GgmbhDEGermanyParticipantEUR 81,738known name (0.95)
Fundacio Privada Barcelona Digital Centre TecnologicESSpainParticipantEUR 166,076PIC (1.00)
Isotrol SAESSpainParticipantEUR 220,150PIC (1.00)
Cardiff UniversityGBUnited KingdomParticipantEUR 265,218known name (0.95)
The Provost, Fellows, Foundation Scholars & the Other Members of Board, of the College of the Holy & Undivided Trinity of Queen Elizabeth Near DublinIEIrelandParticipantEUR 279,781PIC (1.00)
Centro di Ricerche Europeo di Tecnologie Design e MaterialiITItalyParticipantEUR 378,150PIC (1.00)
Matrix SRLITItalyParticipantEUR 264,390PIC (1.00)
Tera SRLITItalyParticipantEUR 104,460PIC (1.00)
Stichting Hoger Beroepsonderwijs HaaglandenNLNetherlandsParticipantEUR 87,460known name (0.95)
Stichting Smart HomesNLNetherlandsParticipantEUR 155,840PIC (1.00)
Woningstichting de ZalighedenNLNetherlandsParticipantEUR 91,400PIC (1.00)

Changes of the consortium

First seen on with 13 participants from 6 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.