FP7
I2C
Integrated System for Interoperable sensors & Information sources for Common abnormal vessel behaviour detection & Collaborative identification of threat
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 48 months
- Total cost
- EUR 15,962,707
- EU contribution
- EUR 9,869,622
- Participants
- 18 from 7 countries
- Topic
- FP7_SEC-2009-3.2-02
- Grant agreement
- 242340
Coordinated by Naval Group (FRFrance).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Naval Group | FRFrance | Coordinator | EUR 1,754,533 | known name (0.95) |
| Clearpriority S.A. | BEBelgium | Participant | EUR 575,560 | PIC (1.00) |
| Eric van Hooydonk | BEBelgium | Participant | EUR 214,000 | PIC (1.00) |
| Jrc -Joint Research Centre- European Commission | BEBelgium | Participant | EUR 431,212 | PIC (1.00) |
| Deutsche Zeppelin-Reederei GmbH | DEGermany | Participant | EUR 363,544 | PIC (1.00) |
| ZLT Zeppelin Luftschifftechnik GmbH & Co KG | DEGermany | Participant | EUR 290,269 | PIC (1.00) |
| Meteosim SL | ESSpain | Participant | EUR 233,750 | PIC (1.00) |
| Ajeco Oy | FIFinland | Participant | EUR 461,574 | PIC (1.00) |
| Furuno Finland Oy | FIFinland | Participant | EUR 652,040 | PIC (1.00) |
| Airshipvision International SA | FRFrance | Participant | EUR 286,473 | PIC (1.00) |
| Association Pour la Recherche et le Developpement des Methodes et Processus Industriels | FRFrance | Participant | EUR 299,008 | PIC (1.00) |
| Intuilab | FRFrance | Participant | EUR 283,865 | PIC (1.00) |
| Rockwell Collins France Sas | FRFrance | Participant | EUR 440,954 | PIC (1.00) |
| Sofresud | FRFrance | Participant | EUR 265,289 | PIC (1.00) |
| Ses Techcom SA | LULuxembourg | Participant | EUR 422,681 | PIC (1.00) |
| Kongsberg Norcontrol As | NONorway | Participant | EUR 835,420 | PIC (1.00) |
| Kongsberg Spacetec As | NONorway | Participant | EUR 200,000 | PIC (1.00) |
| Name not shown | Not stated | Participant | Not stated | PIC (1.00) |
Changes of the consortium
First seen on with 18 participants from 7 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.