Skip to content

H2020

BERTIM

Building energy renovation through timber prefabricated modules

Programme
Horizon 2020
Started
Ends
Duration
48 months
Total cost
EUR 4,914,210
EU contribution
EUR 4,148,435
Participants
16 from 7 countries
Topic
H2020_EE-01-2014
Grant agreement
636984

Coordinated by Fundacion Tecnalia Research & Innovation (ESSpain).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Fundacion Tecnalia Research & InnovationESSpainCoordinatorEUR 946,470PIC (1.00)
Dietrichs AGDEGermanyThird partyNot statedPIC (1.00)
Technische Universitaet MuenchenDEGermanyParticipantEUR 299,966PIC (1.00)
Brabrand BoligforeningDKDenmarkParticipantEUR 3,940known name (0.95)
Egoin SAESSpainParticipantEUR 310,555PIC (1.00)
Empresa Municipal de la Vivienda y Suelo de Madrid SAESSpainParticipantEUR 105,665known name (0.97)
Dietrich's FranceFRFranceParticipantEUR 618,380PIC (1.00)
Institut Technologique Fcba (Foretcellulose Bois-Construction Ameublement)FRFranceParticipantEUR 267,244VAT number (0.97)
Pobi StructuresFRFranceParticipantEUR 278,910PIC (1.00)
Oslo KommuneNONorwayParticipantEUR 2,333known name (0.95)
Asm Research Solutions Strategy Spolka z Ograniczona OdpowiedzialnosciaPLPolandParticipantEUR 261,250PIC (1.00)
Collage Arkitekter ABSESwedenParticipantEUR 15,459PIC (1.00)
Lulea Tekniska UniversitetSESwedenParticipantEUR 195,424known name (0.95)
Martinsons Byggsystem KbSESwedenParticipantEUR 9,128PIC (1.00)
Rise Research Institutes of Sweden ABSESwedenParticipantEUR 385,000known name (0.95)
Setra Travaror ABSESwedenParticipantEUR 448,711PIC (1.00)

Changes of the consortium

First seen on with 16 participants from 7 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.