PowerUp

Specification, Implementation, Field Trial, and Standardisation of the Vehicle-2-Grid Interface

Programme
Seventh Framework Programme
Started
Ends
Duration
24 months
Total cost
EUR 3,544,246
EU contribution
EUR 2,413,515
Participants
10 from 7 countries
Topic
FP7_GC-ICT-2011.6.8
Grant agreement
285285

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Denso Automotive Deutschland GmbHDEGermanyParticipantEUR 318,510PIC (1.00)
Institut Europeen des Normes de Telecommunication AssociationFRFranceParticipantEUR 128,260PIC (1.00)
Itron France SasFRFranceParticipantEUR 163,370PIC (1.00)
Dimosia Epicheirisi Ilektrismou Anonymi EtaireiaGRGreeceParticipantEUR 90,120PIC (1.00)
Erevnitiko Panepistimiako Institouto Systimaton Epikoinonion Kai YpologistonGRGreeceParticipantEUR 251,600PIC (1.00)
Systema Teknolotzis Anonymi Etaireia Efarmogon Ilektronikis Kai PliroforikisGRGreeceParticipantEUR 113,735PIC (1.00)
Centro Ricerche Fiat ScpaITItalyParticipantEUR 170,000PIC (1.00)
Technolution BVNLNetherlandsParticipantEUR 273,634PIC (1.00)
Volvo Technology ABSESwedenParticipantEUR 220,000PIC (1.00)
Corinex Communications AsSKSlovakiaParticipantEUR 328,416PIC (1.00)

Changes of the consortium

First seen on with 10 participants from 7 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.