OPtimization of a Thermal energy Storage system with integrated Steam Generator

Programme
Seventh Framework Programme
Started
Ends
Duration
36 months
Total cost
EUR 13,726,034
EU contribution
EUR 8,649,500
Participants
10 from 7 countries
Topic
FP7_ENERGY.2011.2.5-1
Grant agreement
283138

Coordinated by Agenzia Nazionale Per le Nuove Tecnologie, L'Energia e Lo Sviluppo Economico Sostenibile (ITItaly).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Agenzia Nazionale Per le Nuove Tecnologie, L'Energia e Lo Sviluppo Economico SostenibileITItalyCoordinatorEUR 1,412,838PIC (1.00)
The Cyprus Research and Educational FoundationCYCyprusParticipantEUR 516,702PIC (1.00)
Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung EvDEGermanyParticipantEUR 711,788known name (0.95)
Centro de Investigaciones Energeticas Medioambientales y TecnologicasESSpainParticipantEUR 443,290VAT number (0.97)
Cobra Instalaciones y Servicios S.AESSpainParticipantEUR 2,300,625PIC (1.00)
Centre National de la Recherche Scientifique CnrsFRFranceParticipantEUR 370,000known name (0.95)
Weizmann Institute of ScienceILIsraelParticipantEUR 265,000PIC (1.00)
Ansaldo Nucleare SpAITItalyParticipantEUR 171,875PIC (1.00)
KT - Kinetics Technology SpAITItalyParticipantEUR 1,525,198PIC (1.00)
Laboratorio Nacional de Energia e Geologia I.P.PTPortugalParticipantEUR 292,670known name (0.95)

Changes of the consortium

First seen on with 10 participants from 7 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.