FP7
PhotonicRoadSME
Development of Advanced Technology Roadmaps in Photonics and Industrial Adaption to SMEs
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 29 months
- Total cost
- EUR 825,023
- EU contribution
- EUR 799,981
- Participants
- 11 from 5 countries
- Topic
- FP7_ICT-2007.3.5
- Grant agreement
- 224572
Coordinated by Steinbeis Innovation Ggmbh (DEGermany).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Steinbeis Innovation Ggmbh | DEGermany | Coordinator | EUR 177,558 | known name (0.95) |
| Karlsruher Institut fuer Technologie | DEGermany | Participant | EUR 33,944 | known name (0.95) |
| Optecnet Deutschland Ev | DEGermany | Participant | EUR 65,204 | PIC (1.00) |
| Steinbeis GmbH & Co KG Fur Technologie Transfer | DEGermany | Participant | EUR 0 | PIC (1.00) |
| Universitaet Karlsruhe (Technische Hochschule) | DEGermany | Participant | EUR 58,224 | PIC (1.00) |
| Asociation Industrial de Optica Color e Imagen (Aido) | ESSpain | Participant | EUR 70,072 | PIC (1.00) |
| Universidad Complutense de Madrid | ESSpain | Participant | EUR 73,442 | known name (0.95) |
| Iin Micropolis OY | FIFinland | Participant | EUR 90,670 | PIC (1.00) |
| Association Pole Optique Rhone-Alpes | FRFrance | Participant | EUR 86,176 | PIC (1.00) |
| Chambre de Commerce et D'Industrie de Region Bourgogne | FRFrance | Participant | EUR 92,220 | PIC (1.00) |
| Instytut Wysokich Cisnien Polskiej Akademii Nauk | PLPoland | Participant | EUR 52,471 | known name (0.97) |
Changes of the consortium
First seen on with 11 participants from 5 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.