Skip to content

H2020

InterFlex

Interactions between automated energy systems and Flexibilities brought by energy market players

Programme
Horizon 2020
Started
Ends
Duration
36 months
Total cost
EUR 22,765,661
EU contribution
EUR 17,009,413
Participants
31 from 8 countries
Topic
H2020_LCE-02-2016
Grant agreement
731289

Coordinated by Enedis (FRFrance).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
EnedisFRFranceCoordinatorEUR 1,970,030known name (0.95)
Ait Austrian Institute of Technology GmbHATAustriaParticipantEUR 1,146,476known name (0.95)
Fronius International GmbHATAustriaParticipantEUR 221,457PIC (1.00)
ElectrabelBEBelgiumThird partyNot statedPIC (1.00)
Engie Energy ManagementBEBelgiumThird partyNot statedPIC (1.00)
Cez Distribuce AsCZCzechiaParticipantEUR 725,513known name (0.95)
Cez Esco AsCZCzechiaThird partyNot statedknown name (0.95)
Cez Solarni, SroCZCzechiaParticipantEUR 400,324PIC (1.00)
Fronius Ceska Republika SroCZCzechiaThird partyNot statedPIC (1.00)
Schneider Electric Cz SroCZCzechiaParticipantEUR 246,266PIC (1.00)
Siemens SroCZCzechiaParticipantEUR 199,548known name (0.95)
Avacon AGDEGermanyParticipantEUR 2,584,192PIC (1.00)
Avacon Netz GmbHDEGermanyThird partyNot statedPIC (1.00)
E.kundenservice Netz GmbHDEGermanyThird partyNot statedPIC (1.00)
E.on Business Services GmbHDEGermanyThird partyNot statedPIC (1.00)
Rheinisch-Westfaelische Technische Hochschule AachenDEGermanyParticipantEUR 1,459,902PIC (1.00)
Accenture SasFRFranceParticipantEUR 191,983PIC (1.00)
Electricite de FranceFRFranceParticipantEUR 496,235known name (0.95)
EngieFRFranceParticipantEUR 564,531known name (0.95)
Engie Global MarketsFRFranceThird partyNot statedPIC (1.00)
Grdf SAFRFranceParticipantEUR 516,829known name (0.95)
Grid Solutions SasFRFranceParticipantEUR 634,467known name (0.95)
SocomecFRFranceParticipantEUR 250,371PIC (1.00)
Siemens SpAITItalyThird partyNot statedPIC (1.00)
Enexis Netbeheer BVNLNetherlandsParticipantEUR 1,221,674known name (0.95)
Enexis Personeel BVNLNetherlandsThird partyNot statedknown name (0.95)
Nederlandse Organisatie Voor Toegepast Natuurwetenschappelijk Onderzoek TnoNLNetherlandsParticipantEUR 420,425known name (0.95)
Stichting ElaadnlNLNetherlandsParticipantEUR 551,367PIC (1.00)
E on Energidistribution ABSESwedenThird partyNot statedknown name (0.95)
E.on Energilosnigar AktiebolagSESwedenThird partyNot statedPIC (1.00)
E.on Sverige ABSESwedenParticipantEUR 2,745,777PIC (1.00)

Changes of the consortium

First seen on with 31 participants from 8 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.