IMPACTS

The impact of the quality of CO2 on transport and storage behaviour

Programme
Seventh Framework Programme
Started
Ends
Duration
36 months
Total cost
EUR 5,573,556
EU contribution
EUR 4,000,765
Participants
12 from 8 countries
Topic
FP7_ENERGY.2012.5.2.2
Grant agreement
308809

Coordinated by Sintef Energi As (NONorway).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Sintef Energi AsNONorwayCoordinatorEUR 1,117,545PIC (1.00)
Tsinghua UniversityCNChinaParticipantEUR 82,800PIC (1.00)
Ge Carbon Capture GmbHDEGermanyParticipantEUR 182,400PIC (1.00)
Gfz Helmholtz-Zentrum Fur GeoforschungDEGermanyParticipantEUR 551,850known name (0.97)
Ruhr-Universitaet BochumDEGermanyParticipantEUR 377,730PIC (1.00)
Fundacion Ciudad de la Energia - Ciuden, F.S.P.ESSpainParticipantEUR 546,456VAT number (0.97)
Progressive Energy LimitedGBUnited KingdomParticipantEUR 339,330PIC (1.00)
Rina Consulting - Centro Sviluppo Materiali SpAITItalyParticipantEUR 204,778PIC (1.00)
Nederlandse Organisatie Voor Toegepast Natuurwetenschappelijk Onderzoek TnoNLNetherlandsParticipantEUR 431,961known name (0.95)
Dnv AsNONorwayParticipantEUR 90,400PIC (1.00)
Equinor Energy AsNONorwayParticipantEUR 12,875known name (0.95)
Institutul de Studii Si Proiectari Energetice SARORomaniaParticipantEUR 62,640PIC (1.00)

Changes of the consortium

First seen on with 12 participants from 8 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.