FP7

GINSENG

Performance Control in Wireless Sensor Networks

Programme
Seventh Framework Programme
Started
Ends
Duration
42 months
Total cost
EUR 4,657,837
EU contribution
EUR 3,099,416
Participants
10 from 6 countries
Topic
FP7_ICT-2007.3.7
Grant agreement
224282

Coordinated by University College Cork - National University of Ireland, Cork (IEIreland).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
University College Cork - National University of Ireland, CorkIEIrelandCoordinatorEUR 367,600VAT number (0.97)
University of CyprusCYCyprusParticipantEUR 312,400known name (0.95)
Sap SeDEGermanyParticipantEUR 753,808PIC (1.00)
Technische Universitaet BraunschweigDEGermanyParticipantEUR 280,530PIC (1.00)
University of LancasterGBUnited KingdomParticipantEUR 351,294PIC (1.00)
Faculdade Ciencias e Tecnologia da Universidade de CoimbraPTPortugalParticipantEUR 460,200PIC (1.00)
Galp Energia Sgps SA*PTPortugalParticipantEUR 0PIC (1.00)
Petrogal SAPTPortugalParticipantEUR 204,947PIC (1.00)
Universidade de CoimbraPTPortugalParticipantEUR 0known name (0.95)
Rise Sics ABSESwedenParticipantEUR 368,637PIC (1.00)

Changes of the consortium

First seen on with 10 participants from 6 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.