NERA

Network of European Research Infrastructures for Earthquake Risk Assessment and Mitigation

Programme
Seventh Framework Programme
Started
Ends
Duration
48 months
Total cost
EUR 12,014,029
EU contribution
EUR 9,000,000
Participants
29 from 15 countries
Topic
FP7_INFRA-2010-1.1.27
Grant agreement
262330

Coordinated by Eidgenoessische Technische Hochschule Zuerich (CHSwitzerland).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Eidgenoessische Technische Hochschule ZuerichCHSwitzerlandCoordinatorEUR 972,500PIC (1.00)
Ait Austrian Institute of Technology GmbHATAustriaParticipantEUR 264,500known name (0.95)
Universitat LinzATAustriaParticipantEUR 149,000PIC (1.00)
VCE Holding GmbHATAustriaParticipantEUR 777,000PIC (1.00)
Österreichisches Forschungs- und Prüfzentrum Arsenal Ges.m.b.h.ATAustriaParticipantNot statedPIC (1.00)
Katholieke Universiteit LeuvenBEBelgiumParticipantEUR 160,000PIC (1.00)
Gfz Helmholtz-Zentrum Fur GeoforschungDEGermanyParticipantEUR 424,000known name (0.97)
Karlsruher Institut fuer TechnologieDEGermanyParticipantEUR 80,000known name (0.95)
Agencia Estatal Consejo Superior de Investigaciones CientificasESSpainParticipantEUR 105,000PIC (1.00)
Association Centre Sismologique Euro-MediterraneenFRFranceParticipantEUR 563,000PIC (1.00)
Centre National de la Recherche Scientifique CnrsFRFranceParticipantEUR 534,500known name (0.95)
Cambridge Architectural Research LimitedGBUnited KingdomParticipantEUR 87,500PIC (1.00)
The University of LiverpoolGBUnited KingdomParticipantEUR 80,000PIC (1.00)
University of LeicesterGBUnited KingdomParticipantEUR 60,000known name (0.95)
Aristotelio Panepistimio ThessalonikisGRGreeceParticipantEUR 250,500PIC (1.00)
Ethniko Asteroskopeio AthinonGRGreeceParticipantEUR 177,000PIC (1.00)
Institouto Technikis Seismologias Kai Antiseismikon KataskevonGRGreeceParticipantEUR 60,106PIC (1.00)
Organismos Antiseismikou Sxediasmou Kai Prostasias (Oasp Eppo Earthquake Planning and Protection Organization)GRGreeceParticipantEUR 19,894PIC (1.00)
Vedurstofa IslandsISIcelandParticipantEUR 122,500PIC (1.00)
AMRA - Analisi e Monitoraggio del Rischio Ambientale ScarlITItalyParticipantEUR 305,500PIC (1.00)
Centro Europeo di Formazione e Ricerca in Ingegneria SismicaITItalyParticipantEUR 415,000PIC (1.00)
Istituto Nazionale di Geofisica e VulcanologiaITItalyParticipantEUR 744,000known name (0.95)
Koninklijk Nederlands Meteorologisch Instituut-KnmiNLNetherlandsParticipantEUR 1,367,500known name (0.95)
Stichting OrfeusNLNetherlandsParticipantEUR 41,000PIC (1.00)
Stiftelsen NorsarNONorwayParticipantEUR 200,000PIC (1.00)
Fundacao da Faculdade de Ciencias da Universidade de Lisboa FpPTPortugalParticipantEUR 80,000PIC (1.00)
Institutul National de Cercetare-Dezvoltare Pentru Fizica PamantuluiRORomaniaParticipantEUR 185,000known name (0.95)
Bogazici UniversitesiTRTürkiyeParticipantEUR 501,500PIC (1.00)
Middle East Technical UniversityTRTürkiyeParticipantEUR 177,000PIC (1.00)

Changes of the consortium

First seen on with 29 participants from 14 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.