FP7
CYSPA
European CYber Security Protection Alliance
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 30 months
- Total cost
- EUR 2,036,632
- EU contribution
- EUR 1,740,000
- Participants
- 20 from 8 countries
- Topic
- FP7_ICT-2011.1.4
- Grant agreement
- 318355
Coordinated by European Organisation for Security (BEBelgium).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| European Organisation for Security | BEBelgium | Coordinator | EUR 301,521 | PIC (1.00) |
| Confederation of Organisations in Road Transport Enforcement Aisbl | BEBelgium | Participant | EUR 103,415 | PIC (1.00) |
| Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung Ev | DEGermany | Participant | EUR 86,100 | known name (0.95) |
| Sap Se | DEGermany | Participant | EUR 96,801 | PIC (1.00) |
| Atos Spain SA | ESSpain | Participant | EUR 149,907 | PIC (1.00) |
| Universidad Politecnica de Madrid | ESSpain | Participant | EUR 76,558 | known name (0.95) |
| Airbus Cybersecurity Sas | FRFrance | Participant | EUR 54,527 | PIC (1.00) |
| Airbus Ds Sas | FRFrance | Participant | EUR 0 | PIC (1.00) |
| Thales Services Numeriques Sas | FRFrance | Participant | EUR 98,306 | PIC (1.00) |
| Associazione Trento Rise | ITItaly | Participant | EUR 671 | PIC (1.00) |
| Engineering - Ingegneria Informatica SpA | ITItaly | Participant | EUR 184,310 | PIC (1.00) |
| Selex Es SpA | ITItaly | Participant | EUR 0 | PIC (1.00) |
| Selex Sistemi Integrati SpA | ITItaly | Participant | EUR 85,065 | PIC (1.00) |
| Telecom Italia SpA o Tim SpA | ITItaly | Participant | EUR 1,223 | PIC (1.00) |
| Universita Degli Studi di Trento | ITItaly | Participant | EUR 61,067 | known name (0.95) |
| Nederlandse Organisatie Voor Toegepast Natuurwetenschappelijk Onderzoek Tno | NLNetherlands | Participant | EUR 59,617 | known name (0.95) |
| Thales Edisoft Portugal, S.A. | PTPortugal | Participant | EUR 0 | PIC (1.00) |
| Visionware-Sistemas de Informacao SA | PTPortugal | Participant | EUR 63,292 | PIC (1.00) |
| STM Savunma Teknolojileri Muhendislik ve Ticaret A.S. | TRTürkiye | Participant | EUR 53,651 | PIC (1.00) |
| Name not shown | Not stated | Participant | Not stated | PIC (1.00) |
Changes of the consortium
First seen on with 20 participants from 8 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.