Skip to content

FP7

A2PBEER

Affordable and Adaptable Public Buildings through Energy Efficient Retrofitting

Programme
Seventh Framework Programme
Started
Ends
Duration
54 months
Total cost
EUR 10,259,963
EU contribution
EUR 6,500,000
Participants
23 from 11 countries
Topic
FP7_EeB.NMP.2013-3
Grant agreement
609060

Coordinated by Fundacion Tecnalia Research & Innovation (ESSpain).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Fundacion Tecnalia Research & InnovationESSpainCoordinatorEUR 1,122,365PIC (1.00)
CAE Services GEIEBEBelgiumParticipantEUR 127,692PIC (1.00)
Conseil des Architectes D'EuropeBEBelgiumParticipantNot statedPIC (1.00)
Acciona Construccion SAESSpainParticipantEUR 403,678PIC (1.00)
Ente Vasco de la EnergiaESSpainParticipantEUR 137,052known name (0.95)
Isoleika Koop.elk. S CoopESSpainParticipantEUR 365,848PIC (1.00)
Universidad del Pais Vasco/ Euskal Herriko UnibertsitateaESSpainParticipantEUR 471,340known name (0.95)
Alpes Isere Habitat Office Public de L'HabitatFRFranceParticipantEUR 36,300PIC (1.00)
HEP - Esco Doo za Vodenje i Financiranje Projekata Energetske UcinkovitostiHRCroatiaParticipantEUR 34,013PIC (1.00)
Abud Mernokiroda KftHUHungaryParticipantEUR 104,908PIC (1.00)
Limerick Institute of TechnologyIEIrelandParticipantEUR 261,833known name (0.95)
Balcke-Durr Energy Solutions S.P.AITItalyParticipantEUR 217,913PIC (1.00)
Rina Consulting SpAITItalyParticipantEUR 378,450PIC (1.00)
Oslo KommuneNONorwayParticipantEUR 116,440known name (0.95)
Bergamo Tecnologie SpzooPLPolandParticipantEUR 803,946PIC (1.00)
CWS Comfort Window System ABSESwedenParticipantEUR 8,553PIC (1.00)
Ivl Svenska Miljoeinstitutet ABSESwedenParticipantEUR 407,931PIC (1.00)
Malmo KommunSESwedenParticipantEUR 581,375known name (0.95)
Parans Solar Lightning ABSESwedenParticipantEUR 285,231PIC (1.00)
Saltx Technology ABSESwedenParticipantEUR 249,434PIC (1.00)
Afliva Danismanlik Ve Egitim Merkezi Iktisadi IsletmesiTRTürkiyeParticipantEUR 223,679PIC (1.00)
Ekodenge Muhendislik Mimarlik Danismanlik Ticaret Anonim SirketiTRTürkiyeParticipantEUR 109,920PIC (1.00)
Ministry of National EducationTRTürkiyeParticipantEUR 52,100PIC (1.00)

Changes of the consortium

First seen on with 23 participants from 11 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.