FP7
CASI
Public Participation in Developing a Common Framework for Assessment and Management of Sustainable Innovation
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 42 months
- Total cost
- EUR 4,378,995
- EU contribution
- EUR 3,897,381
- Participants
- 20 from 12 countries
- Topic
- FP7_SiS.2013.1.2-1
- Grant agreement
- 612113
Coordinated by Applied Research and Communications Fund (BGBulgaria).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Applied Research and Communications Fund | BGBulgaria | Coordinator | EUR 615,996 | PIC (1.00) |
| Zentrum Fuer Soziale Innovation | ATAustria | Participant | Not stated | PIC (1.00) |
| Zentrum Fur Soziale Innovation GmbH | ATAustria | Participant | EUR 257,100 | PIC (1.00) |
| Katholieke Universiteit Leuven | BEBelgium | Participant | EUR 195,810 | PIC (1.00) |
| Kliynteh Bulgaria Fondatsiya | BGBulgaria | Participant | EUR 47,133 | PIC (1.00) |
| TechnoLogica EAD | BGBulgaria | Participant | EUR 59,438 | PIC (1.00) |
| Futures Diamond Sro | CZCzechia | Participant | EUR 225,877 | PIC (1.00) |
| Technische Universitat Dortmund | DEGermany | Participant | EUR 198,164 | known name (0.97) |
| Fonden Democracy X | DKDenmark | Participant | EUR 411,614 | PIC (1.00) |
| Helsingin Yliopisto | FIFinland | Participant | EUR 194,764 | known name (0.95) |
| Kuluttajatutkimuskeskus | FIFinland | Participant | EUR 75,016 | PIC (1.00) |
| The University of Manchester | GBUnited Kingdom | Participant | EUR 287,970 | known name (0.95) |
| Comune di Monza | ITItaly | Participant | EUR 65,591 | known name (0.95) |
| Meta Group SRL | ITItaly | Participant | EUR 210,006 | PIC (1.00) |
| Universita' Degli Studi di Milano-Bicocca | ITItaly | Participant | EUR 104,592 | known name (0.95) |
| Fundacja Uniwersytetu Im Adama Mickiewicza w Poznaniu | PLPoland | Participant | EUR 135,248 | PIC (1.00) |
| Increase Time SA | PTPortugal | Participant | EUR 65,591 | PIC (1.00) |
| Inova+ - Innovation Services, SA | PTPortugal | Participant | EUR 230,618 | PIC (1.00) |
| Municipio de Espinho | PTPortugal | Participant | EUR 59,438 | known name (0.95) |
| Univerza na Primorskem Universita del Litorale | SISlovenia | Participant | EUR 126,741 | known name (0.95) |
Changes of the consortium
First seen on with 20 participants from 12 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.