PJ28 IAO

Integrated Airport Operations

Programme
Horizon 2020
Started
Ends
Duration
39 months
Total cost
EUR 5,066,923
EU contribution
EUR 3,546,846
Participants
19 from 13 countries
Topic
H2020_SESAR.IR-VLD.Wave1-22-2015
Grant agreement
731787

Coordinated by Deutsches Zentrum Fur Luft - Und Raumfahrt Ev (DEGermany).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Deutsches Zentrum Fur Luft - Und Raumfahrt EvDEGermanyCoordinatorEUR 1,212,233known name (0.97)
Honeywell International SroCZCzechiaThird partyNot statedPIC (1.00)
Rizeni Letoveho Provozu Ceske Republiky Statni PodnikCZCzechiaParticipantEUR 12,660known name (0.95)
Integra Consult AsDKDenmarkThird partyNot statedPIC (1.00)
Indra Sistemas SAESSpainParticipantEUR 700,000PIC (1.00)
AirbusFRFranceParticipantEUR 102,181PIC (1.00)
Airbus Operations SasFRFranceThird partyNot statedPIC (1.00)
Honeywell AerospaceFRFranceParticipantEUR 500,001PIC (1.00)
Thales Avs France SasFRFranceParticipantEUR 92,772PIC (1.00)
Airtel Atn LimitedIEIrelandParticipantEUR 0PIC (1.00)
Akcine Bendrove Oro NavigacijaLTLithuaniaParticipantEUR 0known name (0.95)
Stichting Koninklijk Nederlands Lucht - En RuimtevaartcentrumNLNetherlandsParticipantEUR 0PIC (1.00)
Indra Navia AsNONorwayThird partyNot statedPIC (1.00)
Sintef AsNONorwayParticipantEUR 420,000known name (0.95)
Stiftelsen SintefNONorwayParticipantEUR 80,000PIC (1.00)
Polska Agencja Zeglugi PowietrznejPLPolandParticipantEUR 0known name (0.97)
Saab AktiebolagSESwedenParticipantEUR 0PIC (1.00)
Letove Prevadzkove Sluzby Slovenskej Republiky, Statny PodnikSKSlovakiaParticipantEUR 0known name (0.95)
Honeywell International IncUSUnited StatesThird partyNot statedPIC (1.00)

Changes of the consortium

First seen on with 19 participants from 13 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.