Skip to content

H2020

Net-UBIEP

Network for Using BIM to Increase the Energy Performance

Programme
Horizon 2020
Started
Ends
Duration
30 months
Total cost
EUR 995,023
EU contribution
EUR 995,023
Participants
13 from 7 countries
Topic
H2020_EE-14-2016-2017
Grant agreement
754016

Coordinated by Agenzia Nazionale Per le Nuove Tecnologie, L'Energia e Lo Sviluppo Economico Sostenibile (ITItaly).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Agenzia Nazionale Per le Nuove Tecnologie, L'Energia e Lo Sviluppo Economico SostenibileITItalyCoordinatorEUR 146,700PIC (1.00)
Mittetulundusuhing Eesti Timmitud Ehituse TugiruhmEEEstoniaParticipantEUR 42,715PIC (1.00)
Tallinna TehnikaülikoolEEEstoniaParticipantEUR 75,075known name (0.95)
Fundacion Laboral de la ConstruccionESSpainParticipantEUR 61,688PIC (1.00)
Sveuciliste U Zagrebu Gradevinski FakultetHRCroatiaParticipantEUR 50,438known name (0.95)
Agencia Estatal Consejo Superior de Investigaciones CientificasITItalyParticipantEUR 39,175PIC (1.00)
Centro Servizi Aziendale ScarlITItalyParticipantEUR 175,903PIC (1.00)
Viesoji Istaiga Skaitmenine StatybaLTLithuaniaParticipantEUR 45,435PIC (1.00)
Vilniaus Gedimino Technikos UniversitetasLTLithuaniaParticipantEUR 54,900known name (0.95)
Balance & Result Organisatie Adviseurs BVNLNetherlandsParticipantEUR 61,825PIC (1.00)
Stichting IssoNLNetherlandsParticipantEUR 109,983PIC (1.00)
Ustav Vzdelavania a Sluzieb SroSKSlovakiaParticipantEUR 53,813PIC (1.00)
Viaeuropa Competence Centre SroSKSlovakiaParticipantEUR 77,375PIC (1.00)

Changes of the consortium

First seen on with 13 participants from 7 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.